新桥道口安装整体道口板施工组织设计
新桥道口安装整体道口板
施工组织设计
永煤公司铁路运输处
目 录
1 工程施工模式·········································································2 2安装整体道口板工程施工方案···············································2 2.1整体道口板施工人员组织···················································2 2.2整体道口板施工布置平面图···············································3 2.3 整体道口板施工··································································3 2.4施工前准备工作···································································3 2.4.1作业准备···········································································4 2.4.2技术准备···········································································5 2.5材料、机具等摆放位置·························································7 2.6整体道口板铺设纵断面图···················································8 2.7整体道口板铺设施工流程···················································9 2.8铁路验收开通·····································································10 3、施工安全措施·······································································10 3.1铁路方向安全防护·····························································10 3.2公路方向安全防护措施·····················································11 3.3施工现场安全防护措施·····················································11 4施工所需机具、材料·····························································12
4.1所需机具、工器具······························································12 4.2修所需材料··········································································13
新桥道口安装整体道口板施工组织设计
1 工程施工模式
1.1新桥道口属于新桥矿地销公路道口,位于新桥矿铁路专用线DK6+273.4处,现为木枕式橡胶道口板铺面,公路路面宽度12米,公路与铁路为平交,平交道口宽度为12米,由于过往车辆多为拉煤车,载重量大,造成道口铺面板损坏、道口线路病害严重,危极行车安全,为了修复永涡道口破损路面,恢复道口良好状态,保证铁路行车安全,计划对该平交道口铺面进行整体式改造,由铁运处组织施工。
1.2新桥道口为50kg/m钢轨线路,计划采用购进的钢筋混凝土整体道口板和底板,现场吊装铺设,整体道口板①长度为2.5米/块,宽3米,需4块;②长度为2米/块,宽3米,需1块,合计12米,底板共预制12米,使铁路方向整体道口板下部两侧各伸出0.2米,底板下部用半干混凝土压实找平。道口两侧预埋热熔管,具体数量和位置由电务段确定。
2安装整体道口板工程施工方案 2.1整体道口板施工人员组织 施工组织领导小组
组长:张 磊 施工负责人:郑伟
成员:任洪俊 李永泉 夏 飞 李亚峰 徐 强 李汉强 杜国昌 孟红光 责任分工:
张磊:负责施工管理与协调工作; 郑伟:全面负责施工现场管理工作; 任洪俊:负责施工安全管理工作; 李永泉:负责施工技术全面管理工作;
夏飞、徐强、李亚峰负责现场标高控制测量及水准桩定位工作,确保底板、面板标高及平面位置的准确;
李汉强、杜国昌负责劳力组织及施工作业; 孟红光负责施工后勤保障工作。
陈四楼线道口平面布置图
施工队伍:新桥工区、李庄工区共32人。 2.2整体道口板施工布置平面图
线道口板布置平面图(轨型P50)
2.3 整体道口板施工:本次施工,计划一次要点施工完成,同时封锁公路,要点6个小时。
2.4施工前准备工作
粮库线和城郊线道口平面布置图
2.4.1作业准备
2.4.2技术准备
对施工中重点、难点问题,由运输科、工务段共同组织攻关,明确技术保障措施,确保施工速度和质量。
2.4.2.1高程控制
2人专职负责使用水准仪控制施工各阶段高程,要计算好计划高程,方便填写和计算,防止测量错误影响工程施工质量。
在道口4角各设置1个永久性标高控制点,要求详细记录各点相对高差,使各点高程可以相互校对,同时永久性标高控制点可用于后来道口沉降观测。
道口西侧边缘设置木桩控制底板、面板起点位置。 2.4.2.2方向控制:
施工前在底板和面板上表面画出板纵向中心线的位置,施工时使用经纬仪控制方向。
由于是首次使用,施工前现场实际演练操作方法。 2.4.2.3整体板纵向高差、路面坡度预留:
由于通过的汽车集中于中间车道,道口中间部分下沉量将大于两边,易导致线路高低不良、排水不畅,因此,道口铺面设置1.5‰、两边向中间逐渐加高的坡度。
2.4.2.4底板上下部干混凝土层找平方法:
底板下部找平:提前制作后30mm (同底板下部干混凝土厚度)木条,用于控制干混凝土厚度标准,待木条间填入过
量的干混凝土后,使用横向长3.2米的方铝合金管(需测定平直)刮过木条上表面,实现底层垫层找平。
面板下部找平:首先使用提前制作好的40mm (宽)*50mm(高)(同面板下部干混凝土厚度)木条置于面板下部边缘,水准仪控制木条水平,在木条间放置过量的干混凝土,使用横向长度3.2米的平直方铝合金管在放置好的木条上刮过,将过量的干混凝土除去。
2.4.2.5整体板水平方向微量波动
整体道口板面板放置好后,使用经纬仪检查其方向是否平直,如存在少量误差,使用2个10吨扁形千斤顶(或起道器)波动道口板,确保道口板中心线与线路中心线重合。
2.4.2.6电缆防护,预留埋置电缆钢管 ①施工准备
道口路面改造开工前15天,工务段通知电务段计划开工日期,电务段准备配合材料,道口整体道口板施工开工前2天,工务段通知电务段相关人员做好配合准备。
②现场配合
道口整体道口板施工期间,电务段派通信、供电、新桥站信号三工区人员到现场专盯防护,告知工务施工负责人电缆位置,确保电缆不被施工机械破坏。施工机械操作人员要听从电务防护人员安排。
③既有电缆防护:
对新桥道口下埋置的电缆,采用电缆槽防护,防护完毕后浇筑混凝土。
④预留电缆埋置通道
新道口板安装之前,新桥站信号工区在新桥道口一侧埋设80钢管两道,为今后敷设电缆备用。
2.4.2.7整体道口板与现浇路面间空隙预留
在整体道口板挂钩处预留纵横方向15cm*10cm,深度同面板厚度的孔洞,其余地点预留宽2cm 的间隙,便于道口板的吊起和整修。
上述孔洞及间隙的尺寸需实际模拟核对才能最终确定。2.5材料、机具等摆放位置
道口板堆放于道口东南角拦门外三块,其它道口板和地板放在道口西侧公路拐角处,不小于30吨吊车停于施工线路外,把拆除的道口板、木枕及其它零星材料放在道口东侧路肩上,使用2台改装自翻车,把挖出的碴土倒在道口房东侧沟内。
2.6整体道口板铺设纵断面图(标注单位为mm ):
P50整体道床横断面图
P50燕尾槽度为:162mm.轨配件采用弹条Ⅰ型扣件,轨下采用131×10×L通长胶垫.
整体道口板改造后纵断面图
2.7整体道口板铺设施工流程:
2.8铁路验收开通
施工完毕后对铁路进行验收,合格后开通铁路,清理现场,不得存有影响铁路行车的物品、工器具等。
3、施工安全措施 3.1铁路方向安全防护
3.1.1工务段提前设好限速标志,施工完毕后的第一趟列车限速10km/h,列车通过后立即检查线路状态,存在问题
立即采取措施处理,如线路状态良好可撤除限速。
3.1.2封锁:线路施工前工务段派专人办理封锁手续,封锁手续办理完毕后在道口两侧铁路方向距施工地点50米线路中心处,设红色停车信号牌防护,防护完毕后方可施工。施工完毕检查确认没有危及行车安全的隐患后办理销记手续。
3.2公路方向安全防护措施
3.2.1在道口两侧公路方向距施工地点50米处设“前方施工,绕道行驶”施工防护牌。同时在施工防护牌外设3根轨枕防护作业人员安全。
3.2.2距离道口30米处设置施工路栏,封锁公路使用路锥、红白相间彩条旗、旧木枕与通行道路隔开,防护公路。
3.2.3为保障公路方向行车安全,需处保卫科安排4名人员(道口两侧各2名)负责现场保卫和维持交通秩序工作。
3.3施工现场安全防护措施
3.3.1施工前召开全体施工人员安全现场会,进行安全措施贯彻和教育,安排具体施工内容,明确责任分工,传达安全注意事项。
3.3.2副段长郑伟为现场负责人(手机号为[1**********]),同时负责组织现场作业人员按章统一指挥施工,并与车站联系施工相关事宜;王凤岐负责现场安全防护。
3.3.3电器设备、机械操作工作必须持证上岗操作,严
格执行设备的操作规程。
3.3.4整体道口板吊装施工时基坑开挖要注意电缆保护,必须明确电缆的走向、埋深方可开挖。
3.3.5整体板及底板吊装要由专人指挥,做到协调一致,吊装作业人员要戴好安全帽,吊装前吊机司机要明确吊装重量,仔细检查吊装绳索是否牢固、完好,吊装时起重臂下及板下禁止站人,吊装板下落时动作要慢,作业人员统一指挥,防止人身伤害。
3.3.6施工现场任洪俊负责施工安全管理工作, 统一安排施工安全防护、登记、销记、安全防护标志设置及收回等工作。
3.3.7两人或多人搬运笨重物件时,由一人指挥,要达到用劲均匀,动作一致,确保安全。
3.3.8拆道和钉道时人与人之间要隔开三根轨枕空间距离,防止机具碰伤,严禁脚踩钢轨和枕木。
3.3.9施工过程中,所有施工人员要服从施工负责人的统一指挥,相互协作,不得擅作主张,盲目蛮干。
4施工所需机具、材料
4.1所需机具、工器具
4.2所需材料
工务段
二0一0年六月十九日